Hello friends in this post we are going to discuss about Agile for Practitioners Assessment_Delivery Multiple choice questions with answers. Many times when we want to study about Agile for Practitioners Assessment_Delivery. We did not get any reference for our study purpose. I also face the same issue while studying agile or practising agile concept. So for helping the students or employees who are working as agile practitioners for them I am writing this post.

So in this post you will find most related Agile for Practitioners Assessment_Delivery Objective type questions | Agile for Practitioners Assessment_Delivery Practise quiz.

1.In a team that follows agile, how would a team member know what others are working on? Select two that apply.

A.The Product Owner and the Facilitator are responsible for maintaining work transparency.
B.The team should have a daily sync-up.
C.One team member must play the role of coordinator and should share daily
status for each member.
D.They may refer to the backlog maintained in a tool (Jira, Prime, and so on).

Ans: B D

2.Survey Q, Non-scoring: What role are you playing in your team?

A. Product Owner/Product Specialist
B. Team Facilitator/Scrum Master/Release Train Engineer/Coach
C. Developer/Engineer/DevOps Engineer/Automation Engineer/Rel lability Engineer
D. Manual Tester/L1 support/L2 support
E. Q Visual Designer/lnteractive Designer/UI Expert
F. Support function

Ans: C

3.what is an efficient way to ensure that. code working as per the acceptance criteria/business requirements?

A. Through automated functional test

B. Through automated regression test

C. Through automated unit tests.

D. Through automated smoke tests.

Ans: A

4.After a team member writes a piece or code, how can she ensure that It works, before checking it in?

A. Through peer reviews

B. Through functional testing.
C. Through unit testing

Ans: C

5.What would he a suggested way to share and sustain knowledge with members in a team.

A. Sharing of Best practices and lessons learnt through Smalls
B. sharing knowledge through knowledge sharing sessions
C. sharing knowledge through informal conversation, for example, During lunch breaks
D. sharing best practises , lessons learnt and ether topics In a central place where team can collaborate

Ans: D

6.Given a piece of work to be executed in agile, how would you form the agile team?

A. An agile learn must have the required skills. Team size will depend on scope and budget
B. An agile team must have the required skills, headcount being less than 12.
C. An agile team must have experienced people, headcount not exceeding 9

Ans: B

7.What do you Mink is a good way for team members to remain updated on work status at any given time?

A. Having an updated physical /digital Kanban board, Scrum board or any other such board
B. Sharing status through email with all
C. Sharing individual updates wen the Lead and the Lead snaring a consolidated summary with all
D. Sharing and referring status reports Mat are shared daily

Ans: A

8.When a Product Owner adds a new feature / idea in the backlog and dings d up for discussion during refinement session, how should a team respond?

A. As the Product Owner has come up with the new feature, team must agree to implement it
B. Team should analyze the feature/ Idea based on the domain and technical knowledge and suggest improvements / altematives ifany
C. Team must analyze only the technical feasibility before accepting the idea

Ans: B

9.How does an agile team Obtain Clarity On backlog items that May be picked up in upcoming iterations?

A. During iteration planning team discusses backlog items for both current and upcoming iterations.
B. Product Owner and Facilitator detail out the backlog Items planned for upcoming Iterations.
C. There is no need to obtain clarity on backlog items for upcoming aerations in advance
D. Dunne every iterations, team has backlog refinement session with the Product owner for gaming clarity on the backlog items to be picked up in upcoming

Ans: D

10.Survey Q, Nan-scoring: If you are working in a customer facing agile team, who is more mature/ready for Agile?

A. our Tcs team Customer team
B. Our TCS team any Customer team are equal
C. Net Sure
D. Not in customer facing role


Ans: B

11.What happens if the offshore team members are not able to participate in the iteration demo due to time zone/infrastructure issues?

A. No issues. On site members ran have the iteration demo with the Product Owner/Stakeholders – it is a single team anyway
B. offshore members will miss the opportunity to interact with the Product Owner/Stakeholders and get the direct feedback about the Increment they created.
C. No major issue. Since offshore Lead and onsite members participate In One demo with the Product Owner/Stakeholders, they can cascade the feedback back to the offshore members
D. It is a loss as the offshore members will not be able to contribute to ideas related to way of working.

Ans: B

12.When multiple team members are working on a related feature, how often should they integrate their work?

A. Do the integration midway through the iteration
B. After they reach a logical end of creating the functionality
C. In a scheduled daily (or multiple times in a day) frequency
D. In a scheduled weekly (or multiple times in a week) frequency

Ans: C

13.What do you think is the most effective way to ensure that code adheres to good coding standards?

ANS – The code has to pass through static code analysis without any violations

14.HOW does an agile team maintain requirements?

A. Every team member maintains a personal backlog of Items they are
working on,
B. Facilitator/onsite coordinator maintains the requirements and
communicates the tasks to the team members
C. Team maintains requirements in a common Place. such as a
Wiki/ Jira/whiteboard and so on.

Ans: C

15.What would be a standard way for anyone outside an agile team (for example, Delivery Partner of the account, Head of the Enablement Function) to get the status of the work at any point in time? Select the correct option(s) and click Submit.

A. He/she can refer the physical/digital Kanban board, which is maintained by the team
B. All team members need to send email updates to him/her daily
C. He/she can have a status review meeting whenever required.
D. He/she can talk to each team member daily to understand the status

Ans: A

16.When you have more than one agile team working on a single product, which one of the following should be considered? Select the correct option(s) and click Submit.

A. All teams need to have similar agile maturity
B. Teams must participate together in all the agile events.
C. Teams to have regular sync-up meets to manage and reduce the dependencies

Ans: C

17.In the middle of the iteration, how should a team handle requirement changes from the customer? Select the correct option(s) and click Submit
Team should never incorporate any changes during an ongoing iteration,
A. Team can always take up the changes and extend iteration duration, if needed.
B. Team may accept the changes in exchange of existing work item(s), if the Facilitator/Lead conveys the criticality of the changes
C. The team may re-negotiate with the Product Owner provided the changes do not endanger the iteration goal

Ans: C

18.For any meeting (other than the agile events) that team members have among them, what are the points to consider? Select the two correct options. Select the correct option(s) and click Submit.

A.Team must keep number of such meetings minimal
B.Team must not allow such meetings to go beyond an hour.
C.Team must keep duration of such meetings short and timebox based on the agenda
D.Team meetings (other than agile events) need not be timeboxed.

Ans: A,C

19.If you are asked to bring in agile way of working into the way a meeting runs, which one among the listed options will you implement? Select the correct option(s) and click Submit.

A.Meetings must be scheduled with a lead time so that the participants can plan their work better
B.Meetings must be run strictly according to the agenda to reduce digressions
C.Meetings must be facilitated and time-boxed.
D.Facilitator/Team Lead must facilitate discussions but he/she may close
meetings as per preference

Ans: C

20.How does the team know what to work upon during the iteration?

A. The team participates in the iteration planning during which the Lead/Onsite coordinator/Facilitator decides who would work on what.
B. Based on the discussions during iteration planning, team members agree on what each would work on
C. The Facilitator has regular interaction with the Product Owner. He/she guides the team on the tasks to be taken up
D. Iteration plans are shared by Product Owner beforehand, any spill over from last iteration is taken up by default

Ans: B

21.in a team, if someone gets stuck with the selected tasks for the iteration, what is the immediate next step? Select the correct option(s) and click Submit.

A. Without wasting time, the team member has to inform the Lead/Onsite coordinator and take up another task
B. The team member should reach out to other team members for help.
C. The team member should wait for the Team Retrospective to discuss the
issue
D.Team member must inform the Product Owner and pick up another task,

Ans: B

22.Which among the the following is a recommended way to run retrospectives?

ANS – Team discusses how they can improve their way of working and picks up one or two improvment areas for next iteration

23.In an agile team, who is responsible for tracking the tasks?

ANS – All team members are responsible for tracking the tasks in a common place such as a Wiki/Jira/ excel/ physical board/ wall/any other option