Agile MCQ


Hello friends in this post we are going to discuss about Agile MCQ with answers | Agile Multiple choice questions | Agile Objective type questions | Agile Free Question answers

1- What does NOT match with Agile Manifesto?

Contract negotiation over customer collaboration

2- Which of the following statements about changing requirements in software development, are correct?

In traditional way of software development, once the requirements are base lined, further changes should undergo heavy change control process

Organizations must adapt to rapidly changing market conditions to stay relevant in business

3- Which of the following statements BEST describe why Agile is winning?

Agile increases the chances of delivering early business value to the market and quickly incorporate the feedback from the market usage

4- Why were the `practitioners of alternative software development methods` not satisfied with the traditional waterfall method?

Waterfall is not a lightweight process

Waterfall model failed to meet the demand for speed and was not friendly towards changing business needs and priorities

5- Which of the following BEST represent the Scrum approach to planning?

Whole team together does just enough upfront planning followed by continuous planning throughout the project

6- How should work be allocated to the team in a Scrum project?

Team members must volunteer for tasks appropriate to their skills

7- The time box for a Daily Scrum is…

15 minutes

8- Why is the Daily Scrum held at the same time and same place?

The consistency reduces complexity and overhead

9- What BEST describe a Scrum Team?

Small but have enough members to create the Product Increment

Collaborate with each other to self-organize their work

Cross Functional

10- The Product Owner in a Scrum project….

Has the final authority over the prioritization of Product Backlog Items

Collaborates with de developers over prioritization of Product Backlog Items but Product Owner has the final say

11- Noor´s Scrum Team Had a great Sprint Review of a new feature wih their Product Owner. Product Owner was happy new feature, and wanted to release the feature to user. But, the Scrum Team cannot do it themselves because production environment is owned the company´s IT operations team. Scrum Team was directed to create a ticket with IT operations for production release, and wait a week a week for an Ops engineer to manually work on the ticket. What is missing in this environment?

Flow

12- Which one of these is NOT an XP practice?

Extreme Reviews

13 – What is a Kanban Board?

A visible chart depicting the work to be done, work in progress and work done

14 – A Scrum Team works on a 4 weeks Sprint. After few Sprints, the team finds that theyspend more effort on unit testing, as the code base size has increased. What can be BESTrecommended for this team?Select the correct option(s) and click Submit.

Adopt practices like test automation form other frameworks like XP

15 – Design Thinking is another name for Agile Manifesto.Select the correct option(s) and click Submit.

False

16 – Mannar & Company kick started a major cross company project that involved working with multiple business unit leaders to build enterprise wide platform. Impressed by the success of small projects in Agile, company leadership enforced Agile in this transformation project. Shortly after few Sprints, teams witnessed that the Product Owner was not able to build consensus among the business unit leaders on requirements. There were several political aspects behind the collaboration. What went wrong?

Agile is based on trust and collaboration so that consensus can be arrived at quickly. This scenario did not have that atmosphere

17- Which of these are the needed actions to realize TCS vision of “0-4-2”?Select the correct option(s) and click Submit.

Agile Ready Partnership

Agile Ready Workforce

Top-to-bottom Enterprise Agile Company ourselves

Agile Ready Workplace

18 – Jerald is a leader of a TCS customer Account. He learnt that the company´s aspiration onAgile is to become 100% Agile by 2020. He gathered his Agile Experts within the account andasked them for a plan to transition from current way of working to 100% Agile way ofworking as defined in the text book. Jerald correctly understood TCS aspiration.Select the correct option(s) and click Submit.

False

19- TCS Agile vision ´100% Agile by 2020`meansSelect the correct option(s) and click Submit.

TCS to be regarded by the market and our customers as 100% right partner/advisor for Agile Transformations

There should not be any Agile related non-compliance in the project audits

20 – ´Agile for Beginners´ course is intended towards motivating you to learn more about Agile so that you can become Select the correct option(s) and click Submit.

Agile Practitioner

21- Agile Manifesto has… Values and … principles Select the correct option(s) and click Submit

4,12

22- There are two Product Development Teams. Team ToyZon and Team Zon. Team ToyZonfollows traditional way and Team Zon follows Agile way of working. Which team has the higher chance to provide early benefits to the customer? Select the correct option(s) and click Submit.

Team Zon

23 – Which of these is a benefit of Agile?Select the correct option(s) and click Submit.

Reduced Risk

Faster time to market

Ability to respond to changing requirements  Improved collaboration between business and technical team

24 – Match the framework to its author(s) in the order of listing: Scrum; Crytal ; Extreme programming Select the correct option(s) and click Submit.

Ken Schwaber and Jeff Sutherland, Alistair Cockburn, Kent Beck

25 – How is the Agile value “Responding to change over following a plan” addressed in Scrum? Select the correct option(s) and click Submit.

During the Sprint Planning, Development team has all the authority to choose any Product Backlog item to work on

Product Owner can change the plan for next Sprint based on latest market conditions and feedback from last Sprint

26- A good Agile team should exhibit the following qualities …Select the correct option(s) and click Submit.

The team is self-organizing

The team is cross-functional

27- On the last day of the Sprint, a Scrum Team named Almost Done is ready to show their work but requires just 2 more days to complete the testing. What should the Scrum Master recommend? Select the correct option(s) and click Submit.

Close the sprint on time

28- Only these people are allowed to attend Sprint Retrospective Select the correct option(s) and click Submit.

Scrum Team

29 – Product Owner and Scrum Master can be the same person Select the correct option(s) and click Submit.

False

30 – Which of these are Agile estimation techniques? Select the correct option(s) and click Submit.

Planning Poker

T Shirt sizing

31 – Providing additional feature without clear understating of the business need – What is this category of waste? Select the correct option(s) and click Submit.

Over Production

32 – ____________ Improves the flow of business idea through its development and release to users. Select the correct option(s) and click Submit.

DevOps practices


33 – John, a team member, has completed E0 0 Agile for Beginners. He wants to contribute to TCS Agile Vision. He wants to find out what is planned for his account. Whom should he contact for details? Select the correct option(s) and click Submit.

Account Leadership

34 – Agile principles can be only used for software development Select the correct option(s) and click Submit.

False

35 – Kris is an experienced Project Manager with a customer project where he commands the teams and micro manages the team members at task level. How can he help the TCS Agile Vision? Select the correct option(s) and click Submit.

Proactively up-skill with skills needed to work in Agile Roles

36 – Which of these are Scrum anti patterns? Select the correct option(s) and click Submit.

Programmers as one Scrum Team and Testers as another Scrum Team

Scrum Team with 20 members

Sprint duration of 6 weeks

37 – What do all Agile Frameworks have in common? Select the correct option(s) and click Submit.

A prescribed, fixed iteration length

Lightweight approach that allows the self-organized teams to better respond to business requirements

Iterative and Incremental development

A prescribed format for backlog items

38 – Daily Scrum is NOT recommended for collocated teams Select the correct option(s) and click Submit.

False

39 – Which of the following BEST describes the approach for determining the Sprint length in Scrum? Select the correct option(s) and click Submit.

The team must collectively agree on the length of the Sprint based on business need and technical team´s ability; subject to a maximum of one month

40 – The reason for holding regular Sprint Retrospective is Select the correct option(s) and click Submit.

It gives management information to use in team members´ performance reviews

Provides an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint.

41 – Who manages the team´s work during a Sprint? Select the correct option(s) and click Submit.

The team manages the work by self-organization

42 – What is the purpose of Sprint burndown chart? Select the correct option(s) and click Submit.

It is used to measure how much work is yet to be done to reach Sprint goal

43 – Which of the following statements are correct? Select the correct option(s) and click Submit.

Design Thinking is about Product Development. Agile Manifesto is about Software Development

Design Thinking is finding the right things and Agile is about building the right things

44 – Which framework prescribes User Story as the format for backlog items? Select the correct option(s) and click Submit.

Scrum

45 – Juaraz is a TCS Delivery Partner of customer ABC, having an Agile Team in one location. He plans to expand this Agile Team. He arrives at a plan to set up the expanded team in another location. For an effective distributed agile between different locations, what is recommended?

Leverage the guidelines from the TCS Point Of view on distributed agile (Location Independent Agile)

46 – Eric has been working for a customer who has been following Agile for quite some time now. He is quite hands-on with Scrum and acquired PSM I certification already. The customer may soon move to a large scale Agile. Which other certification may be beneficial for Eric sohe can be prepared to help the customer? Select the correct option(s) and click Submit.

SAFe Program Consultant (SPC)

47 – What is MOST likely to happen if the Product Owner is not available during a Sprint? Select the correct option(s) and click Submit.

The Sprint Deliverables may not be of desired value  The Scrum Master plays the role of Product Owner

48 – In Daily Scrum, team members share yesterday´s progress and the plan for next 24 hrs with ___________. Select the correct option(s) and click Submit.

Scrum Master

49 – Sprint itself is an event in Scrum Select the correct option(s) and click Submit.

True

50 – Lee joins a project team that attempts to build a consumer device with embedded software. The team is adopting 2-week sprint. Lee notices that the project must produce an outcome that will be highly adoptable by the users to become successful. After every Sprint Review, the Product Owner keeps changing the Product vision and makes contradictory statements about user needs. What can be suggested for this environment? Select the correct option(s) and click Submit.

Apply design thinking first for initial phase and then bring in Agile later

51 – Increasing number of TCS customers are moving to the Agile way of working. Why is this a true statement? Select the correct option(s) and click Submit.

For Last few years, there is a double digit increment in number of Agile projects (per IPMS) year on year

In 90% of executive conversations, customers bring in Agile as a topic of conversation  For all new engagements, TCS mandates Agile

This is not a true statement

Both 1 and 2

52 – The agile way is: Select the correct option(s) and click Submit.

To produce working software of high business value and of the right quality, early and incrementally

53 – Munna bhai knows the four values of Agile Manifesto by heart. However, he was confused when a customer spoke with him highlighting Agile characteristics of short software development cycles or iterations. He could not recollect anything about short iterations in Agile Manifesto. What did he miss to learn about? Select the correct option(s) and click Submit.

Agile Principles

54 – Industry surveys show that in traditional approach, users do not use nearly 60% of the features delivered. What do you think are the probable causes? Select the correct option(s) and click Submit.

These features were developed based on initial assumptions about the user requirements, but assumption turned out to be wrong

By the time the features were delivered, the market and user requirements had changed.

55 – Which one is a popular tool used in Agile Software development Select the correct option(s) and click Submit.

Jenkins

56 – The Scrum team is using the Kanban board to make work visually available to all. What CANNOT be inferred from the board?

Percentage completion

57 – Martin is from the TCS BPS team. As part of TCS Agile vision, he was recommended to attain E0 competency in Agile. Martin was thinking that Agile was only for software. How could Agile knowledge help Martin in his work?

Agile principles can help in continuously improving BPS processes

58 – Which of these are Agile estimation techniques?

Planning Poker

T-Shirt sizing

59 – The Agile approach to documentation is:

Do just enough documentation to support the development and use of the product

60 – Agile Team need to comply by the Agile Values and Principles but have flexibility to choose appropriate value-adding practices

True

61 – Who owns the Product backlog?

Product Owner

62 – Who owns quality in a Scrum Team?

Scrum Team

63 – Ron has just started as a Scrum Master for an Agile team. He has acquired knowledge by reading multiple sources. After practicing Scrum for a while on the job, he is looking for a certification to benchmark. What can be recommended for him?

Professional Scrum Master I (PSM I)

64 – Which of these are Scrum anti patterns?

Programmers as one Scrum Team and Testers as another Scrum Team

Scrum Team with 20 members

Sprint duration of 6 weeks

65 – What is the propose of Sprint Review?

To inspect the working software with the key stakeholders and take the insights from the feedback to next Sprint


Leave a Reply

Your email address will not be published. Required fields are marked *