Where can you maintain the planned delivery time used for scheduling in material requirements planning? Note: There are

3 correct answers to this question.

A.  Plant parameters

B.  Purchasing info record

C.  Outline agreement

D.  Supplier

E.  Material
closed

1 Answer

0 votes
by (0 points)
 
Best answer
Answers  B D E