Which of the following elements are used during forward scheduling in material requirements planning? Note: There are

2 correct answers to this question.

A.  Total replenishment lead time

B.  Shipping processing time

C.  Goods receipt processing time

D.  Purchasing processing time
closed

1 Answer

0 votes
by (0 points)
 
Best answer
C D