What must you do to enable the creation of Just-in-Time (JIT) delivery schedule lines for a scheduling agreement? Note: There

are 2 correct answers to this question.

A.  Maintain the MRP views in the master record of the material

used in the scheduling agreement item.

B.  Set the JIT indicator in the master record of the material used

in the scheduling agreement item.

C.  Set the JIT Indicator field in the purchasing info record of the

material and supplier used in the scheduling agreement.D.  Use a document type for the scheduling agreement for which

release documentation has been activated.
closed

1 Answer

0 votes
by (0 points)
 
Best answer
B C