should work be allocated to the team in a Scrum project

A.The Scrum Master must assign tasks to individuals
B.Team members must volunteer for tasks appropriate to their skills
C.The complex tasks must be allocated by the Scrum Master
D.Tasks must be allocated to team members by the Product Owner
E.While senior team members volunteer for tasks, juniors must be assigned tasks by the Scrum Master

closed

1 Answer

0 votes
by (0 points)
 
Best answer
b