0 votes
53 views
in Agile by (0 points)
closed by

The Product Owner in a Scrum project

A.Has no control over the prioritization of Product Backlog Items
B.Has the final authority over the prioritization of Product Backlog Items
C.Collaborates with the developers over prioritization of Product Backlog Items, but the developers have the final say
D.Collaborates with the developers over prioritization of Product Backlog Items, but Product Owner has the final say
E.Creates the Product Backlog Items but leaves prioritization to Business Analyst

closed

1 Answer

0 votes
by (0 points)
 
Best answer
B,D