The trend of work remaining across time in a sprint, a release, or a product, with work remaining tracked on the vertical axis and the time periods tracked on the horizontal axis is called?

a. Burndown Chart
b. Parking lot Chart
c. Progress Chart
d. Burnup Chart

closed

1 Answer

0 votes
by (0 points)
 
Best answer
A