A team is referring to the latest version of the product backlog to work on the
deliverables. Who is responsible for the content, availability and ordering of the items in
the product backlog?

a. Product Owner
b. Project Manager 
c. Scrum Master
d. Scrum Development Team

closed

1 Answer

0 votes
by (0 points)
 
Best answer
A