0 votes
115 views
in agile by (0 points)
closed by

A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?

closed

1 Answer

0 votes
by (0 points)
 
Best answer

They are waterfalling the Iteration

Related questions

0 votes
1 answer 82 views
0 votes
1 answer 68 views
0 votes
1 answer 92 views

2.8k questions

2.8k answers

0 comments

76 users

Welcome to MCQ Village Q&A, where you can ask questions and receive answers from other members of the community.
...