0 votes
138 views
in Agile by (0 points)
closed by

Which of the following BEST describes the approach for determining the Sprint length in Scrum?

A.Sprints must be 30 days always
B.Product Owner unilaterally decides the duration of Sprint
C.Sprints must be two weeks always
D.The team must collectively agree on the length of the Sprint based on business need and technical team’s ability; subject to a maximum of one month
E.There is no rule on Sprint duration

closed

1 Answer

0 votes
by (0 points)
 
Best answer
d

Related questions

0 votes
1 answer 109 views
0 votes
1 answer 142 views
0 votes
1 answer 78 views
asked May 30, 2024 in Agile by Admin (0 points)
0 votes
1 answer 110 views
0 votes
1 answer 54 views
asked May 30, 2024 in Agile by Admin (0 points)

2.8k questions

2.8k answers

0 comments

76 users

Welcome to MCQ Village Q&A, where you can ask questions and receive answers from other members of the community.
...