A team has completed 10 Sprints and moving to the 11th Sprint. Till Sprint 10, the team
has achieved an average of 50 story points per sprint. The same is projected as their
velocity for the upcoming sprints with the Client. What is this approach called?
a. Commitment Driven Velocity
b. Velocity Driven Commitment
c. Commitment Driven Sprint Planning
d. Velocity Driven Sprint Planning