After what activity we should raise a Change Request(CR)? (Choose the best option)
a. Any changes to the requirements which come after entering the Design Stage.
Since the requirements gets base lined at the end of Analyze stage.
b. Any changes made after the design is complete
c. Only functional requirement change needs CR
d. Any changes to the requirements which is realized in any stage