Ques:- During the material availability check for a sales order item, the ordered quantity is completely confirmed  on the required date even

though there is only a partial quantity in stock. Which setting could lead to this behavior?
closed

1 Answer

0 votes
by (0 points)
 
Best answer
The Without Replenishment Lead Time indicator is not set in the configuration  of the scope of availability check.