What is a downside of using the traditional Waterfall approach?

A.It requires a larger commitment for collaboration between project team members than Agile.

B It lacks detailed documentation, leading to misunderstandings and difficulties between the team members.

C It can increase costs and delays if updates are incorporated in the development process after the planning stage.

D.It prevents the development team from quantifying the effort, time, and cost of delivering the final product

closed

1 Answer

0 votes
by (0 points)
 
Best answer
c