0 votes
147 views
in TQ by (0 points)
closed by

What is a downside of using the traditional Waterfall approach?

A.It requires a larger commitment for collaboration between project team members than Agile.

B It lacks detailed documentation, leading to misunderstandings and difficulties between the team members.

C It can increase costs and delays if updates are incorporated in the development process after the planning stage.

D.It prevents the development team from quantifying the effort, time, and cost of delivering the final product

closed

1 Answer

0 votes
by (0 points)
 
Best answer
c

Related questions

0 votes
1 answer 56 views
0 votes
1 answer 56 views
asked Dec 31, 2023 in TQ by Admin (0 points)
0 votes
1 answer 75 views
0 votes
1 answer 114 views

2.8k questions

2.8k answers

0 comments

76 users

Welcome to MCQ Village Q&A, where you can ask questions and receive answers from other members of the community.
...